Solar Additions May Fall Below 1GW as Industry Urges Policy Support

Browser TTS · no download

30-second brief

One year after the three solar environmental assessment laws took effect, new additions through September totaled less than 800MW, with full-year additions likely below 1GW. Seven industry associations on the 19th called for destigmatization, urged friendly government support, and said they are willing to communicate with all three parties to bring the industry back on track.

New Additions Drop Sharply One Year After Amendments

Last November the Legislative Yuan passed amendments to the Environmental Impact Assessment Act, the Act for the Development of Tourism and the Geology Act, commonly called the three solar environmental assessment laws, imposing strict controls on ground-mounted and floating solar PV. According to Energy Administration statistics through September this year, new solar installed capacity was less than 800MW, including only 500MW of growth from January to June. Full-year additions are estimated at less than 1GW, below levels during the 2020-2021 pandemic period and far below the 2.6GW connected to the grid in 2023.

Industry Worried About Supply Chain and Green Power Demand

Shen Shang-hung, chairman of the Taiwan Solar Photovoltaic Industry Sustainable Development Association, said annual solar additions previously reached 2 to 3GW, predictable like housing building permits, but case volumes have now fallen markedly, with development possibly returning to 2018 levels. He said that amid social stigmatization and unfriendly regulations, the supply chain from panel manufacturing and PV module systems to invested solar farms has been affected. Operators are not unwilling to invest, but increased barriers have reduced future applications, further affecting technology industries that need green power.

High Review Costs Cloud Application Outlook

On the review burden, Wang Liang-kai, a director of the Taiwan Solar Photovoltaic Industry Association, said that after passage of the three laws, one environmental review costs about NT$1 million to NT$2 million, forming a tight straitjacket around solar. Tsai Chia-chin, honorary chairman of the Taiwan Solar Photovoltaic Industry Sustainable Development Association, said his company currently has 3 cases under environmental review, and worries most that after spending millions to over ten million NT dollars to pass review, it remains unclear whether local governments, the Ministry of Agriculture and the Ministry of the Interior will approve, making investment and outcomes hard to predict.

Industry Willing to Talk With Three Parties, Seeks Destigmatization

Wang Wen-wei, executive director of the Solar Photovoltaic Sustainability Association, said the energy mix should not favor nuclear, wind, solar or thermal power alone, but should combine sources, adding that environmental review conditions for solar are stricter than for thermal power plants or nuclear waste, lacking reasonable logic and scientific judgment. Seven solar industry associations held a press conference on the 19th, calling on society to reduce stigmatization of reservoir-based solar, and saying they are willing to communicate with the government and the three parties and attend public hearings to bring industry development back on track, hoping the government will offer a friendly view and support.

FAQ

What are new additions since the three solar environmental assessment laws took effect?

Through September this year, new solar additions were less than 800MW, including only 500MW from January to June. Full-year additions are estimated at less than 1GW, below 2020-2021 pandemic-period levels and far below the 2.6GW connected in 2023.

What are solar operators asking for?

Seven associations on the 19th called for less stigmatization of reservoir-based solar, urged the government to offer a friendly view and support, and said they are willing to communicate with the government and the three parties and attend public hearings to bring the industry back on track.

Why are operators worried about environmental review and follow-up approvals?

One environmental review costs about NT$1 million to NT$2 million, with total spending potentially reaching millions to over ten million NT dollars. Operators worry that even after passing review, approval by local governments, the Ministry of Agriculture and the Ministry of the Interior remains uncertain, and falling case volumes will hit panels, module systems and green power supply.