Power Demand in Greater Southern Science Park to Reach 8 Million kW
As AI computing demand and advanced semiconductor processes continue to expand, power demand from the Tainan Science Park and surrounding industrial clusters has increased sharply. Taipower estimates that long-term power consumption in the Greater Tainan Science Park will climb to 8 million kW, equivalent to 8000MW. The so-called Greater Tainan Science Park refers not only to the Southern Taiwan Science Park Tainan Park, but covers existing and future development areas including the Tainan Park, the STSP Specific Area, the Shalun Park and the Tree Valley Park, totaling about 20 square kilometers. Taipower estimates that long-term power demand in Tainan City could exceed 10 million kW. Based on about 20 square kilometers, average power density demand is about 400,000 kW per square kilometer, showing highly concentrated power consumption, posing challenges to grid thermal stability, voltage quality and fault tolerance.
109.6 Billion Invested in 3 Major Grid Projects
On the supply construction side, Taipower plans to invest about 109.6 billion to advance transmission and substation construction. This mainly includes building new substations in the STSP Specific Area and Shalun Science Park to enhance power switching and supply capacity in the parks; constructing the 345kV Hsingta to STSP transmission line to strengthen transmission capacity between power plants and the parks; and adding substations in nearby industrial zones to improve the regional supply network. The overall goal is to strengthen regional supply capacity to meet concentrated loads from advanced semiconductor processes and AI computing industries, supporting future expansion of the STSP and Shalun parks.
5 Direct-Supply Lines Involve Separate 155.5 Billion Investment
Taipower also plans to promote direct supply from power plants to science parks to shorten transmission distance from generation to industrial users. The 5 approved park direct-supply dedicated lines involve about 155.5 billion in related project investment, covering Tata, Tunghsiao, Taichung, Hsingta and Talin power plants, expected to be completed and commissioned from 2026 to 2033. Among them, Hsingta Power Plant and Senba Power Plant are planned to support the STSP and Shalun parks, while Talin Power Plant is planned to directly supply the Nanzi Park. Taipower stressed that these direct-supply lines and the 109.6 billion Greater Southern Science Park transmission project are different planning items, and the two budgets should not be confused.
Land Acquisition and Completion Timelines in Focus
Beyond grid construction, Taipower also noted that future power growth in the STSP and Shalun parks still requires local power sources and grid construction. At present, STSP supply mainly relies on support from the Senba Power Plant and Hsingta Power Plant, and Taipower continues to seek additional stable local power sources in Tainan, including the planned Senba Phase III IPP plant. As the Shalun Science Park is expected to start development in 2027, whether Greater Southern Science Park supply construction can keep pace with park development will be a key focus. Land acquisition for substations and transmission lines, construction progress and power source allocation will also affect subsequent semiconductor expansion in Tainan.