TECO adds another offshore wind turnkey track record
TECO Electric & Machinery (1504) announced on November 26 that it has completed a contract signing with Copenhagen Infrastructure Partners (CIP) to undertake the onshore substation turnkey engineering for the Fengmiao No. 2 offshore wind farm. The two parties recently signed the “Fengmiao No. 2 Offshore Wind Onshore Substation Turnkey Engineering” contract and held a kickoff ceremony. Including this project, the onshore substation projects TECO has contracted over the years correspond to a combined wind farm installed capacity of more than 3GW (3 million kilowatts, 3,000MW).
Fengmiao No. 2 at 600MW, grid connection expected in 2030
Fengmiao No. 2 is planned for an installed capacity of 600MW and is one of the first projects to get underway in Taiwan's offshore wind Phase 3 Round 2 (3-2), with grid connection expected in 2030. The onshore substation is responsible for converting the power delivered from the offshore wind farm and transmitting it to Taipower's grid; its construction progress and system reliability are critical to the wind farm's subsequent commercial operation and stable power supply.
Both sides continue their long-term cooperation model
TECO Chairman Ming-Hsien Li said the two sides have cooperated over the long term and have accumulated experience at multiple offshore wind farms; TECO will combine its own power equipment with large-scale electromechanical turnkey experience and deliver on schedule through engineering safety, quality control and project management. Fengmiao No. 2 CEO Mark Wainwright also noted that the two sides will continue their past cooperation model, integrating project management, engineering execution and technology while balancing engineering quality and contract delivery schedule.
Financing targeted for completion before the end of June 2027
CIP Asia Pacific President Nai-Wen Hsu said that with the various engineering contracts falling into place one after another, Fengmiao No. 2 is advancing its financing work, with a target of completing it before the end of June 2027. She noted that the government has made strengthening financial support and optimizing the national financing guarantee mechanism a policy direction for the long-term development of offshore wind, and CIP looks forward to those measures being implemented as soon as possible. Whether Fengmiao No. 2 can complete financing on schedule will also be an indicator for domestic and international markets watching policy effectiveness and Taiwan's offshore wind investment environment.
Market share above 35%; five consecutive awards since 2019
TECO said its market share in Taiwan's offshore wind onshore substation engineering market exceeds 35%, backed by more than seven years of engineering experience. Since 2019, TECO has consecutively won 5 related turnkey projects, with its track record covering the Changfang Xidao, Zhongneng and Fengmiao wind farms.
TECO noted that onshore substation turnkey engineering covers design, equipment procurement, civil construction and electromechanical system integration, and must comply with international technical specifications and engineering management requirements. It can supply medium-voltage transformers, switchgear, emergency generators, busbars and air-conditioning equipment, and support long-term substation operation through after-sales service; during construction it will also use monitoring and management mechanisms to balance engineering quality, operational safety and environmental protection.